Pay Application #4
Keystone Commercial Builders · Riverside Medical Office Building

Voltmark Electric, LLC

Billing period ending July 31, 2026 · Retainage 10.00%
#DescriptionScheduledPrev.This periodStored% doneRetainageBalance
1
Common work results, rough-in
26 05 00
$42,000.00$37,800.0090.00%$3,780.00$4,200.00
2
Conductors & cables
26 05 19
$26,500.00$15,900.0060.00%$1,590.00$10,600.00
3
Panelboards
26 24 16
$18,500.00$7,400.0040.00%$740.00$11,100.00
4
Wiring devices
26 27 26
$11,000.00$0.000.00%$0.00$11,000.00
5
Interior lighting
26 51 00
$34,000.00$0.000.00%$0.00$34,000.00
6
Exterior lighting
26 56 00
$9,000.00$0.000.00%$0.00$9,000.00
7
Added emergency egress lighting (CO #12)
CO-012
$7,500.00$0.000.00%$0.00$7,500.00
Totals$148,500.00$0.00$6,110.00$87,400.00
Certification & signature

By typing your name you certify this application for payment is correct and, upon receipt of payment, waive lien rights through this period.

Completed to date$61,100.00
Materials stored$0.00
Total earned$61,100.00
Less retainage− $6,110.00
Less prior payments− $54,990.00
Current payment due
$0.00
Enter this period's work to continue.